WESTFIELDS TRANSPORTATION NEWS

Westfields Transportation News:

The WBOA has been very concerned with the traffic buildup at Rt 66 and Rt 28.   Traffic has increased over the years to include very real safety concerns on Rt 66 and Rt 28 in the AM and PM rush hours.  The WBOA will continue to push our County, State, and Federal officials to make this a priority for resolution.   We ask that all property owners, tenants, and employees, homeowners get involved and let your elected official know how concern you are.  Also get engaged and aware of these and other issues by joining the Dulles Area Transportation Association (DATA)

VDOT has now opened up a study on this issue.   Please see the link to VDOT's Rt 66/28 website for this project.

With the help from Supervisor Frey's office, we have provided you a list of road transportation improvements to help alleviate some of the traffic congestion in and around Westfields:

Stringfellow Road – Widen from two to four lanes from Fair Lakes Boulevard to Route 50

Advertisement – July 2012 – Begin construction -UNDERWAY – Completion – Summer 2015

Estimated cost - $63 million

Route 50 – Widen from four lanes to six lanes from Route 28 to Poland Road (Design-Build)

Construction UNDERWAY – Completion December 2015

Estimated cost - $99.9 million

Route 29 Bridge over Little Rocky Run – Replace existing bridge – new bridge built to six-lane capacity (Design-Build)

Advertisement – July 2012 - Begin construction – Late 2013 – Completion – mid-2015

Estimated cost - $14.5 million

Walney Road Bridge over Flatlick Branch – Replace existing bridge – new bridge built to a four-lane capacity with bike lanes

Construction Date:  UNDERWAY Completion – October 2015

This project might be done as a design-build, which would accelerate the schedule (begin construction Fall 2013 – completion Summer 2014)

Estimated cost - $7 million

Walney Road – Widen from two to four lanes from 250 feet south of Mariah Court to Willard Road

Construction Date:  UNDERWAY

Estimated cost - $8.491 million (VDOT believes the total cost will be lower)

Walney Road/Willard Road – Upgrade existing traffic signal (mast arms to replace span wire and install pedestrian signals and ADA ramps)

Advertise – August 2012 – Construction – UNDERWAY

Estimated Cost - $402,000

Lee Road Widening/Culvert – Extend the box culvert and widen Lee Road over Schneider Branch

Advertise – December 2013 – Begin construction 2014 – Completion – COMPLETED

Estimated cost - $4.2 million

Route 28 northbound extend Walney Road turn lane past the Walney Road intersection

Advertise - Work order is in the process and once approved, work will begin. Completion – COMPLETED

Estimated cost - $1.2 million

Route 28 southbound – extend dual turn at I-66 eastbound ramp

Advertise – March 2013 – COMPLETED

Estimated cost - $2 million

Fairfax County Parkway/Fair Lakes Parkway Interchange Parkway

Construction underway – Completion – October 2013

Estimated cost $69.2 million

Stonecroft Boulevard 3rd Lane expansion – widen Southbound lane from Marriott service entrance to Westfields Boulevard. Begin construction – 2nd Qtr 2015.